How to build a manpower loading chart from a GC schedule.

Turn the GC's P6 or MS Project schedule into a crew forecast for your trade, and keep it current every time the schedule changes.

A manpower loading chart shows how many people your trade needs on site each day or week of the job. GCs ask subs for one, and it is how you plan hiring, overtime and moves between jobs. Here is how to build one from the GC's schedule, by hand and the faster way.

For the thinking behind the numbers, read how to plan crew from a schedule you did not write.

What you need

  • The GC's schedule. The PDF is fine.
  • Your labour hours for each scope of work, from your estimate.
  • The hours one person really produces in a day. Six to seven is realistic on a good job, not eight.

How to build a manpower loading chart in Excel

  1. Copy your trade's activities and their start and finish dates out of the GC's PDF.
  2. Spread each scope's hours over its activities, by how many working days each runs.
  3. Divide each activity's hours by its working days and the hours per person-day. That is its crew.
  4. Add the crews up by day or week and chart them. The tallest bar is your peak.
  5. Redo all of it when the GC sends the next update.

Step five is the problem. Schedules change every month, so a spreadsheet chart is out of date soon after you build it.

The faster way: a manpower loading chart in GanttAI

  1. Upload the GC's schedule PDF. GanttAI reads every activity and finds the ones in your scope.
  2. Enter your hours per scope and hours per person-day, once for the project.
  3. Get crew per trade by day, week or month, with each trade's busiest day.
  4. When the next update arrives, upload it. The crew plan follows the new dates by itself, and a comparison shows the crew impact.
  5. Change any figure by hand where you know better. The totals follow.
  6. Export the crew plan to Excel to send to the GC.

Questions subs ask

Do I have to enter a crew for every activity? No. You enter hours per scope once. The schedule divides them.

What happens when the GC changes the schedule? Upload the new version. Your hours carry over and the chart follows the new dates.

Can I see all my jobs on one chart? Yes, on the Portfolio plan.

Can I try it free? Yes. The free trial is 1 project, 2 schedule reviews and 1 comparison between them, with no card.

Build your manpower loading chart.

Upload the GC's schedule, enter your hours once, and the chart keeps up with every update.